Found at: http://www.hlurb.gov.ph/article/articleprint/2053/-1/256/
|
Approval of Housing Permits under EO 45
|
|
Top level
HLURB Final
Developers
EO 45 prescribes specific period for a government agency and the local government units to act on applications for certifications, clearances and permits for housing projects (i.e. subdivisions or condominiums). It also provides an option for the applicant-developer where the government agency or LGU refuses or fails to dispose of an application for said applied for housing permit.
Untitled Document
The following is an outline of said EO:
- Filing
Applications for the issuance of housing related certifications,
clearances or permits may be filed simultaneously with local government unit
(sangguniang pambayan or panglunsod) and each of the other government agencies
(DAR, DENR, etc.). These agencies shall accept and process the applications
without prerequisite housing related permit/s from other government agencies.
- Processing
If the documentary requirements are complete, the government agency shall
accept and process the application and, if meritorious, shall issue within
the time period under Section 6 of EO 45 the applied for certification, clearance
or permit. If not meritorious, the agency shall issue within the same period
a written decision/order of denial stating the grounds thereof.
- Opposition to application
In case an opposition is filed against the proposed project, the concerned
government agency concerned shall resolve the opposition. The period during
the pendency of shall not be counted against the agency.
- Time period to act on application
EO 45 prescribes time periods in the processing of housing related certifications,
clearance and permits, for each government agency and the local government
unit to wit:
- HLURB
- Certificate of Site Zoning Classification – 10 days
- Certificate of Registration and License to Sell
– 10 days
- DAR
- Conversion Order or Exemption Order – 30 days
- MARO Certification – 10 days
- CLUPP 1 Certification – 30 days
- DENR
- DENR Secretary/Regional Director
ECC – 45 days
- DENR Secretary/Regional Director
NIPAS Certification – 15 days
- DENR Assistant Regional Executive Director
Verification and Approval of Survey Returns – 30 days
- MGB Director
EGGAR – 10 days
- LLDA Administrator
LLDA Certification – 15 days
- Department of Agriculture
- DA Secretary or Regional Director
Certification for Reclassification of Agri Land – 30 days
- NIA
- NIA Regional Manager
Irrigation Clearance Certificate - 15 days
- Philippine Coconut Authority PCA Administrator
PCA Clearance Certification - 15 days
- Sugar Regulatory Administration
SRA Clearance Certification - 15 days
- LGU
- Development Permit – 30 days
- Failure/Refusal to dispose application
Should the responsible official of the government agency concerned
fails or refuses to dispose application by either approving or denying the
same within the prescribed period, the applicant, if not expressly prohibited
by law, may submit an affidavit, with supportive technical studies and documents
by competent individuals, in lieu of the certification, clearance or permit.
- Sanctions to responsible officer for refusal/failure to dispose
application
If the responsible official refuses/fails to dispose application within the
prescribed period, said official shall be liable for administrative sanctions
provided for by law.
EO 45 is reproduced en toto for your reference