Approval of Housing Permits under EO 45


Top level HLURB Final Developers

EO 45 prescribes specific period for a government agency and the local government units to act on applications for certifications, clearances and permits for housing projects (i.e. subdivisions or condominiums). It also provides an option for the applicant-developer where the government agency or LGU refuses or fails to dispose of an application for said applied for housing permit.

Untitled Document

The following is an outline of said EO:

  1. Filing
    Applications for the issuance of housing related certifications, clearances or permits may be filed simultaneously with local government unit (sangguniang pambayan or panglunsod) and each of the other government agencies (DAR, DENR, etc.). These agencies shall accept and process the applications without prerequisite housing related permit/s from other government agencies.
  2. Processing
    If the documentary requirements are complete, the government agency shall accept and process the application and, if meritorious, shall issue within the time period under Section 6 of EO 45 the applied for certification, clearance or permit. If not meritorious, the agency shall issue within the same period a written decision/order of denial stating the grounds thereof.
  3. Opposition to application
    In case an opposition is filed against the proposed project, the concerned government agency concerned shall resolve the opposition. The period during the pendency of shall not be counted against the agency.
  4. Time period to act on application
    EO 45 prescribes time periods in the processing of housing related certifications, clearance and permits, for each government agency and the local government unit to wit:
  5. Failure/Refusal to dispose application
    Should the responsible official of the government agency concerned fails or refuses to dispose application by either approving or denying the same within the prescribed period, the applicant, if not expressly prohibited by law, may submit an affidavit, with supportive technical studies and documents by competent individuals, in lieu of the certification, clearance or permit.
  6. Sanctions to responsible officer for refusal/failure to dispose application
    If the responsible official refuses/fails to dispose application within the prescribed period, said official shall be liable for administrative sanctions provided for by law.

EO 45 is reproduced en toto for your reference